Failed EICR

Former Community Member
Former Community Member

Hi just want to know what you guys and girls do in the following situation. 

You've carried out an EICR its failed. 

Once the remedials have been carried out do you redo the original EICR so it's Satisfactory?

Or do you fill out minor works certs and give these to the customer along with the original failed report so once cross referenced  it results in being satisfactory. 

This has been bugging me for awhile now. 

Regards TS

Parents
  • Former Community Member
    0 Former Community Member

    Alan, 

    This was my thinking, that way you have a record of findings and supportive MWC to backup any corrective works. 

    Unfortunately some sparks seem to think just changing the unsatisfactory to satisfactory outcome is sufficient ?

    Regards TS

Reply
  • Former Community Member
    0 Former Community Member

    Alan, 

    This was my thinking, that way you have a record of findings and supportive MWC to backup any corrective works. 

    Unfortunately some sparks seem to think just changing the unsatisfactory to satisfactory outcome is sufficient ?

    Regards TS