Failed EICR

Former Community Member
Former Community Member

Hi just want to know what you guys and girls do in the following situation. 

You've carried out an EICR its failed. 

Once the remedials have been carried out do you redo the original EICR so it's Satisfactory?

Or do you fill out minor works certs and give these to the customer along with the original failed report so once cross referenced  it results in being satisfactory. 

This has been bugging me for awhile now. 

Regards TS

Parents
  • I have noticed something horribly interesting after my post above, and that is that there have been NO comments on what I said. I really would like some feedback, because I would like to understand WHY it has been ignored. Does anyone even understand the post? Do you understand the QS system? Perhaps you all think it is fine and works really well? It relates to the OP in a clear way, Fred does an EICR, Bert comes from the same company to fix some defects, who knows what he actually did and the QS signs an MWC. Is this now satisfactory, or is it a big no one knows, or does the QS issue a new satisfactory EICR? I have a few examples of each! Some must be wrong, or perhaps not…..

Reply
  • I have noticed something horribly interesting after my post above, and that is that there have been NO comments on what I said. I really would like some feedback, because I would like to understand WHY it has been ignored. Does anyone even understand the post? Do you understand the QS system? Perhaps you all think it is fine and works really well? It relates to the OP in a clear way, Fred does an EICR, Bert comes from the same company to fix some defects, who knows what he actually did and the QS signs an MWC. Is this now satisfactory, or is it a big no one knows, or does the QS issue a new satisfactory EICR? I have a few examples of each! Some must be wrong, or perhaps not…..