Hi
I work on a site supplied by 2 substations, each at 600A per phase
The subs are quite heavily loaded.
Just as a rough guide... what would be the complete cost to install a third substation of a similar size?
The IET is carrying out some important updates between 17-30 April and all of our websites will be view only. For more information, read this Announcement
Hmm that will depend where it is, how much ground work is needed, if the HV lines already go where they would be needed or if they too need to be upscaled. The DNO should be able to advise. And the biggy of course - are these DNO transformers or customer private ones ?
Some of the DNOs do publish indicative charge information - this is quite an old doc from EON but gives some ideas. Click here
The problem is you could take numbers from pages 8-10 of that doc and easily find they double or half depending on the specific requirements of your site, and it is pretty much ten years out of date. I suggest sitting down when you call the DNO. Be prepared to not blink at £50k.
Mike.
Hmm that will depend where it is, how much ground work is needed, if the HV lines already go where they would be needed or if they too need to be upscaled. The DNO should be able to advise. And the biggy of course - are these DNO transformers or customer private ones ?
Some of the DNOs do publish indicative charge information - this is quite an old doc from EON but gives some ideas. Click here
The problem is you could take numbers from pages 8-10 of that doc and easily find they double or half depending on the specific requirements of your site, and it is pretty much ten years out of date. I suggest sitting down when you call the DNO. Be prepared to not blink at £50k.
Mike.