DPC PUBLISHED FOR 18TH EDITION AMD 3

I had an email this morning from the IET telling me that a Draft for Public Consultation has been published for Amendment 3 to BS 7671.

Details here  electrical.theiet.org/.../

JP

Parents
  • Seems to have now been posted to BSI, comprising the changes suggested by Lyle and Andy (I haven't checked if they are verbatim).

    If this is all it is... I confess I need to check the books but is this not already a requirement?

    Also, to have been rushed out in this fashion, presumably this is in response to a specific incident(s)? Either way would it not be reasonable for BSI/IET to publish a supporting note justifying the change; this should illustrate where there is a (percieved) deficiency / gap in the existing standard.

  • Technical question wth regards to Amendment 3.
    Will this be classed as a C1 or C2 on an EICR if a Unidirectional is fitted rather than a Bi-Direction if it is fitted to Micro-Generation like a Car2Grid or when doing PV to Grid?  Also would it require a replacement breaker as the wording in the proposed Regulation states SHALL?  

  • Sorry have just gone back and looked, the IET say on the BS7671 portal

    The amendment follows a bulletin from BEAMA which aimed to clarify the differences between connections for unidirectional and bidirectional RCDs and circuit-breakers.

    which would appear to refer to this

    https://www.beama.org.uk/resourceLibrary/beama-technical-bulletin---connection-of-unidirectional-and-bidirectional-protective-devices.html

Reply Children
No Data