Domestic 2 phase system and additional single phase supply.

Hi everyone, a domestic refurb has an existing 2phase supply. The DNO cut-out is arranged like a standard PME system. Is it reasonable to use the same earth terminal for both phases. I guess this is the same as what would be standard for a 3phase system, only in this instance 2phases. Additionally our client has applied for another single phase supply that is to enter site at another location, therefore 2 supplies onto one site. The DNO seem happy with this though I find it unusual as commercial projects do not seem to like two PME supplies onto one site?