opinions of C2 code on satisfactory EICR

I am about to audit a property tested by a contractor.

on the report it has a C2 code but also states rectified, while we like a record of repairs and the previous code assigned, im not sure its correct to have a C2 on a satifactory EICR?

Parents Reply Children
  • So if there was no SPD at all. Then why was the observation given that there was no indication of functionality? After one was fitted by the person doing the eicr, and that one had no indication, then why did they fit it, knowing it would get a C3?

    This before and after mash up leads to confusion. I don't particularly care if the certification bodies' inspectors think it is ok, it is not clear and understandable. If there needs to be a record of remedial works done on the day, I suggest it should be put in the "comments on the existing installation" box, and a clean, satisfactory report issued.